Deck moved to our Seawind shed on 6th October for the first Assembly stage. Work is being carried out on transom extension. Hull is in our driveway waiting for some Lam parts to be handed over. Deck joining is scheduled for 20th October, 2020.
Production Update – Assembly
Production Update – Assembly Stage
Production Update – Fit out
It is excited that your boat is progressing well in the Fit out stage.
We have successfully completed several major structural and exterior installation works, including the engines, stanchion, and A-frame.
Our Production team is currently working on deck hardware (60%), plumbing & LPG (70%), electric work (50%), steering (50%), timber fitout (30%).
















Production Update – Fit out
Your boat is progressing well in the Fit out stage.
We have successfully completed several major structural and exterior installation works, including the A-frame, stanchions, forward beam, as well as the installation of all windows and hatches.
Our Production team is currently working on trampoline, deck hardware (90%), electric work (80%), plumbing & LPG (80%), steering (70%), and timber fitout (65%).


















Production Update – Fit out
Your boat is progressing well in the Fit out stage.
We recently completed the installation of A-frame, stanchions, forward beam, windows and hatches.
Our Production team is currently working on trampoline, deck hardware (95%), electrical items (95%), plumbing & LPG (90%), steering (90%), and timber fitout (85%).















Production Update – Lamination
An exciting journey has started. Your boat is making progress in the first stage of production – Lamination.
As you can see in the photos, the deck and some furniture infusion have been completed. The hull demoulding is scheduled to take place soon, and we are now working on the installation of the steel alignment jigs and bulkheads.






Production Update – Assembly
Your boat is progressing well in the Assembly stage.
As shown in the attached photos, at this stage, the hull deck interior laminations have been completed, the engine and exhaust system installation have been completed. The hull-deck joint is also finished and we’re now working on exterior gelcoat repair.













Production Update – Assembly
Your boat is making progress in one of the first stages of production – Assembly.
At this point, the wall liner installation and the ceiling panel frames have been completed. Our team has also installed the glass on board.
Currently, we’re working on exterior gelcoat repairs, interior gelcoat repairs, and the electrical system (5% complete).















Production Update – Detailing & QA
Your boat has been progressing well in the Detailing & QA stage, where several additional components have been completed to bring it closer to the final stages.
Our team has recently completed several critical systems, including the fuel system, bilge system, freshwater system, seawater system, black water system, and LPG system.
Currently, we are working on the electrical system (80% complete), all timberwork installation (95% complete), and the ventilation system (90% complete).

















Production Update – Detailing & QA
Your boat has been progressing well in the Detailing & QA stage, where several additional components have been completed to bring it closer to the final stages.
At this stage, we have completed the bilge system, freshwater system, seawater system, and black water system.
We are currently working on the electrical system (45%), timberwork (60%), fuel system (98%), ventilation system (50%), and LPG system (50%).