Deck moved to our Seawind shed on 6th October for the first Assembly stage. Work is being carried out on transom extension. Hull is in our driveway waiting for some Lam parts to be handed over. Deck joining is scheduled for 20th October, 2020.
Production Update – Fitout
Thank you for purchasing the beautiful Seawind 1160XL, and welcome to the Seawind family. An exciting journey has just begun, and we are pleased to let you know that your boat is progressing well through the Fit-out stage.
At this stage, the deck has been joined, and the IGU work has been completed. We have also installed several components, including the engines, forward beam, trampoline, stanchions, targa seat, and stainless-steel davits.
We are currently working on the windows and hatches (60%), deck hardware (70%), electrical system (15%), plumbing (40%), timber fit-out (40%), and steering system (35%).



















Production Update – Assembly
Production Update – Assembly
Production Update – Assembly
Production Update – Assembly
Production Update – Fit out
Production Update – Fit out
Production Update – Completion
We are excited to announce that CATALYST is now completed and moved to the storage yard, ready for launching.
Please see below for some photos of the boat in her final days before being launched. Let us also take you on a tour around your boat via this Youtube video.
It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1370.








































































Production Update – Fitout
Your boat has moved to the next stage of production – Fitout.
The boat has recently been fitted with several components, marking significant progress in the build process. At this stage, our team has completed several critical components, including the BHD liner (carpentry), ceiling panel frames, fuel system, and bilge system.
We are now working on the electrical system (10% complete), bilge system, black water system, and window installation (90% complete).