Deck moved to our Seawind shed on 6th October for the first Assembly stage. Work is being carried out on transom extension. Hull is in our driveway waiting for some Lam parts to be handed over. Deck joining is scheduled for 20th October, 2020.
Production Update – Fit out
Your boat is progressing well in the Fit out stage.
We have finished the installation of windows & dech hatches, forward beam, A-frame & A frame wire, and engines.
Our Production team is currently working on deck hardware (80%), plumbing (70%), steering (70%), electric (50%), and timber fitout (30%).















Production Update – Fit out
Your boat is progressing well in the Fit out stage.
We finished the installation of stanchions, forward beam, A-frame, A-frame wire, all windows, and the deck hatches. Our Production team is currently working on deck hardware (80%), plumbing (80%), steering (70%), timber fitout (70%) and electrical items (70%).












Production Update – Fit out
Your boat is progressing well in the last phase of Fit out stage.
The boat is currently at 85% of completion progress. Electrical system, plumbing system, engines, deck hardware & navigation instrument have been installed successfully & tested. Timber fitout & upholstery are on on track. With this progress, the boat will be finished on time for shipping as planned.















Production Update – Detailing & QA
Production Update – Assembly
Your boat is progressing well in the Assembly stage.
The targa bar and door bulkhead are currently being installed on the deck. The coachroof will be installed once this work is complete. Meanwhile, our Assembly team is making good progress installing the interior furniture modules throughout the hull.






Production Update – Assembly
Production Update – Assembly
Your boat is progressing well in the last phase of Assembly stage.
We recently completed the installation of engines, deck hatches, forward beam, A-frame, stanchions, jib track & traveller, main sheet traveller track, winches, and deck organizer.
Our Production team is currently working on window installation, electric (15%), plumbing (20%), steering system (50%), and deck hardware (70%).


















Production Update – Fit out
We are excited to inform you that your boat has been moved to the Fit out stage.
We have recently completed the installation of the windows, deck hatches, forward beam, A-frame, and engines. Our Production team is currently working on deck hardware (70%), plumbing (50%), steering (50%), electric (25%), and timber fitout (25%).


















Production Update – Fit out
Your boat is progressing well in the Fit out stage.
Installation of the engines, deck hardware, and navigation instruments has been successfully completed, with all systems tested and confirmed to be functioning correctly. The timber fit-out and upholstery are progressing smoothly and have now reached approximately 80% completion, keeping the boat production on track for the planned delivery schedule.