Production Update – Assembly 1

Deck moved to our Seawind shed on 6th October for the first Assembly stage. Work is being carried out on transom extension. Hull is in our driveway waiting for some Lam parts to be handed over. Deck joining is scheduled for 20th October, 2020.

Production Update – Fitout

Thank you for purchasing the beautiful Seawind 1160XL, and welcome to the Seawind family. An exciting journey has just begun, and we are pleased to let you know that your boat is progressing well through the Fit-out stage.

At this stage, the deck has been joined, and the IGU work has been completed. We have also installed several components, including the engines, forward beam, trampoline, stanchions, targa seat, and stainless-steel davits.

We are currently working on the windows and hatches (60%), deck hardware (70%), electrical system (15%), plumbing (40%), timber fit-out (40%), and steering system (35%).

Production Update – Assembly

Your boat is progessing well in the Assembly stage.

The deck has been finished and demolded, ready to be joined with the coach roof. Our Lamination team is currently proceeding with the installation of the furniture modules inside the hull.

Production Update – Assembly

Your boat is progressing well in the Assembly stage.

The hull has been completed with all initial plumbing, hoses, and thru-hulls installed. The deck is also fully prepared and ready for assembly. The hull-to-deck joining is scheduled to take place in the following weeks.

Production Update – Assembly

Your boat is progressing well in the Assembly stage.

The hull and deck joining process was successfully completed. Our Production team is currently working on the engine preparation, pre-plumbing installation, and gelcoat repair.

Production Update – Assembly

Your boat is taking the final steps in the last phase of Assembly stage.

We recently completed the installation of the engines.
Our Production team is currently working on windows (50%), deck hardware (25%), electrical work and plumbing at 25%.

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

We recently have completed the installation of windows, hatches, and deck hardware.
Our Production Team is currently working on flooring, electrical items (90%), plumbing system (90%), and timber fitout (90%).

Production Update – Completion

We are excited to announce that CATALYST is now completed and moved to the storage yard, ready for launching.

Please see below for some photos of the boat in her final days before being launched. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1370.

Production Update – Fitout

Your boat has moved to the next stage of production – Fitout.

The boat has recently been fitted with several components, marking significant progress in the build process. At this stage, our team has completed several critical components, including the BHD liner (carpentry), ceiling panel frames, fuel system, and bilge system.

We are now working on the electrical system (10% complete), bilge system, black water system, and window installation (90% complete).

Production Update – Lamination

Your boat is progressing well in the Lamination stage.

All BHDs and webs have been installed, and all omegas have been bonded to the hull. At this point, the deck is ready for the hull-to-deck join. We are currently working on the exterior hull gelcoat repairs and the IGU.