Production Update – Assembly 1

Deck moved to our Seawind shed on 6th October for the first Assembly stage. Work is being carried out on transom extension. Hull is in our driveway waiting for some Lam parts to be handed over. Deck joining is scheduled for 20th October, 2020.

Production Update – Assembly

Your boat is progressing well in the Assembly stage.

The targa bar and door bulkhead are currently being installed on the deck. The coachroof will be installed once this work is complete. Meanwhile, our Assembly team is making good progress installing the interior furniture modules throughout the hull.

Production Update – Assembly

Your boat is progressing well in the Assembly stage.

The hull and deck joining has been succesfully completed. Our Production team is currently working on gelcoat repair, preparation for engines & deck hardware installation.

Production Update – Assembly

Your boat is progressing well in the last phase of Assembly stage.

We recently completed the installation of engines, deck hatches, forward beam, A-frame, stanchions, jib track & traveller, main sheet traveller track, winches, and deck organizer.
Our Production team is currently working on window installation, electric (15%), plumbing (20%), steering system (50%), and deck hardware (70%).

Production Update – Fit out

We are excited to inform you that your boat has been moved to the Fit out stage.

We have recently completed the installation of the windows, deck hatches, forward beam, A-frame, and engines. Our Production team is currently working on deck hardware (70%), plumbing (50%), steering (50%), electric (25%), and timber fitout (25%).

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

Installation of the engines, deck hardware, and navigation instruments has been successfully completed, with all systems tested and confirmed to be functioning correctly. The timber fit-out and upholstery are progressing smoothly and have now reached approximately 80% completion, keeping the boat production on track for the planned delivery schedule.

Production Update – Fitout

Thank you for purchasing the beautiful Seawind 1160XL, and welcome to the Seawind family. An exciting journey has just begun, and we are pleased to let you know that your boat is progressing well through the Fit-out stage.

At this stage, the deck has been joined, and the IGU work has been completed. We have also installed several components, including the engines, forward beam, trampoline, stanchions, targa seat, and stainless-steel davits.

We are currently working on the windows and hatches (60%), deck hardware (70%), electrical system (15%), plumbing (40%), timber fit-out (40%), and steering system (35%).

Production Update – Assembly

Your boat is progessing well in the Assembly stage.

The deck has been finished and demolded, ready to be joined with the coach roof. Our Lamination team is currently proceeding with the installation of the furniture modules inside the hull.

Production Update – Assembly

Your boat is progressing well in the Assembly stage.

The hull has been completed with all initial plumbing, hoses, and thru-hulls installed. The deck is also fully prepared and ready for assembly. The hull-to-deck joining is scheduled to take place in the following weeks.

Production Update – Assembly

Your boat is progressing well in the Assembly stage.

The hull and deck joining process was successfully completed. Our Production team is currently working on the engine preparation, pre-plumbing installation, and gelcoat repair.