Production Update – Assembly 1

Deck moved to our Seawind shed on 6th October for the first Assembly stage. Work is being carried out on transom extension. Hull is in our driveway waiting for some Lam parts to be handed over. Deck joining is scheduled for 20th October, 2020.

Production Update – Assembly

It is excited that your boat has been moved to the Assembly stage.

The hull has been successfully demolded and is now in the IGU stage, while the deck and coach roof are scheduled for production shortly.

Production Update – Assembly

We are excited to inform you that your boat has been moved to the Assembly stage.

The hull was successfully demolded, and our Lamination team is currently proceeding with the installation of the furniture modules inside the hull. At the same time, the deck and coach roof are being fabricated in their respective molds. With the current progress, the hull-to-deck joining is expected to take place soon.

Production Update – Assembly

Your boat is progressing well in the Assembly stage.

The hull has been completed with all initial plumbing, hoses, and thru-hulls installed. The deck is also fully prepared and ready for assembly. The hull-to-deck joining is scheduled to take place within this week.

Production Update – Assembly Stage

Your boat is progressing well in the Assembly stage.

The hull & deck joining process was successfully completed. Our Production team is currently working on the engine preparation, pre-plumbing installation, and first stage of the electrical system, including wiring layout and conduit preparation.

Production Update – Fit out

It is excited that your boat is progressing well in the Fit out stage.

We have successfully completed several major structural and exterior installation works, including the engines, stanchion, and A-frame.
Our Production team is currently working on deck hardware (60%), plumbing & LPG (70%), electric work (50%), steering (50%), timber fitout (30%).

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

We have successfully completed several major structural and exterior installation works, including the A-frame, stanchions, forward beam, as well as the installation of all windows and hatches.
Our Production team is currently working on trampoline, deck hardware (90%), electric work (80%), plumbing & LPG (80%), steering (70%), and timber fitout (65%).

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

We recently completed the installation of A-frame, stanchions, forward beam, windows and hatches.
Our Production team is currently working on trampoline, deck hardware (95%), electrical items (95%), plumbing & LPG (90%), steering (90%), and timber fitout (85%).

Production Update – Lamination

An exciting journey has started. Your boat is making progress in the first stage of production – Lamination.

As you can see in the photos, the deck and some furniture infusion have been completed. The hull demoulding is scheduled to take place soon, and we are now working on the installation of the steel alignment jigs and bulkheads.

Production Update – Assembly

Your boat is progressing well in the Assembly stage.

As shown in the attached photos, at this stage, the hull deck interior laminations have been completed, the engine and exhaust system installation have been completed. The hull-deck joint is also finished and we’re now working on exterior gelcoat repair.

Production Update – Assembly

Your boat is making progress in one of the first stages of production – Assembly.

At this point, the wall liner installation and the ceiling panel frames have been completed. Our team has also installed the glass on board.

Currently, we’re working on exterior gelcoat repairs, interior gelcoat repairs, and the electrical system (5% complete).