Deck moved to our Seawind shed on 6th October for the first Assembly stage. Work is being carried out on transom extension. Hull is in our driveway waiting for some Lam parts to be handed over. Deck joining is scheduled for 20th October, 2020.
Production Update – Detailing & QA
Your boat is progressing well in the Detailing & QA stage.
Several key components have been successfully completed such as deck hardware, stainless steel parts, windows & hatches.
In the meantime, significant progress continues across the remaining systems onboard, with electrical installation currently approximately 80% complete, plumbing and LPG systems at around 85%, steering installation at 90%, and the timber fitout progressing steadily at approximately 80%.

































Production Update – Fit out
We are excited to inform you that your boat is progressing well in the Fit out stage.
Several key components have been successfully completed such as stainless steel parts, windows & hatches.
Our Production team is currently working on deck hardware (75%), electrical work (25%), plumbing (50%), steering (50%), and timber fitout (50%).



























Production Update – Assembly
Production Update – Assembly
We are excited to inform you that your boat has been moved to the Assembly stage.
The hull was successfully demolded, and our Lamination team is currently proceeding with the installation of the furniture modules inside the hull. At the same time, the deck and coach roof are being fabricated in their respective molds. With the current progress, the hull-to-deck joining is expected to take place soon.









Production Update – Assembly
Production Update – Assembly Stage
Production Update – Fit out
It is excited that your boat is progressing well in the Fit out stage.
We have successfully completed several major structural and exterior installation works, including the engines, stanchion, and A-frame.
Our Production team is currently working on deck hardware (60%), plumbing & LPG (70%), electric work (50%), steering (50%), timber fitout (30%).
















Production Update – Fit out
Your boat is progressing well in the Fit out stage.
We have successfully completed several major structural and exterior installation works, including the A-frame, stanchions, forward beam, as well as the installation of all windows and hatches.
Our Production team is currently working on trampoline, deck hardware (90%), electric work (80%), plumbing & LPG (80%), steering (70%), and timber fitout (65%).


















Production Update – Fit out
Your boat is progressing well in the Fit out stage.
We recently completed the installation of A-frame, stanchions, forward beam, windows and hatches.
Our Production team is currently working on trampoline, deck hardware (95%), electrical items (95%), plumbing & LPG (90%), steering (90%), and timber fitout (85%).















Production Update – Lamination
An exciting journey has started. Your boat is making progress in the first stage of production – Lamination.
As you can see in the photos, the deck and some furniture infusion have been completed. The hull demoulding is scheduled to take place soon, and we are now working on the installation of the steel alignment jigs and bulkheads.