Deck moved to our Seawind shed on 6th October for the first Assembly stage. Work is being carried out on transom extension. Hull is in our driveway waiting for some Lam parts to be handed over. Deck joining is scheduled for 20th October, 2020.
Production Update – Fit out
Your boat has been progressing well in the Fit out stage.
The boat is now approximately 90% complete. Our Production team is currently finalizing plumbing and LPG (90%), electrical works (80%), navigation systems (80%), and timber fit-out (90%). With this progress, the boat remains on track for launching as scheduled.












Production Update – Fitout
Your boat is now in the Fit-out stage where we have started to work on the key parts and the preparations for windows in.
At this point, the deck joining has taken place, and our team has also completed work on the longeron and gelcoat repairs. We are currently working on deck hardware, stanchion, lifelines, electrical system, and plumbing.
























Production Update – Details & QA
Production Update – Assembly
Production Update – Fitout
The current status shows that your boat is progressing well in the Fitout 2 stage.
Recently, some key components on the boat have been completed, including deck hardware, windows & hatches, and electric propulsion.
We are now working on steering system (90%), plumbing (75%), electrical system (35%), and timber fitout (65%).

































Production Update – Assembly
Production Update – Fit out
We are excited to inform you that your boat is progressing well in the Fit out stage.
We recently completed the installation of A-frame, stanchion, forward beam, windows and hatches. Our Production team is currently working on trampoline, deck hardware (50%), electric work (30%), plumbing & LPG (30%), steering (30%).













Production Update – Assembly
Production Update – Fitout
Your boat has been progressing well in the Fit-out stage and was recently equipped with some critical components.
At this stage, we have already installed the forward beam, A-frame, anchor box, windows and trampoline. We are now working on the deck hardware (95%), steering system (25%), plumbing & LPG (50%), electrical system (15%), and timber fitout (50%).





























Production Update – Fit out
Your boat is progressing well in the Fit out stage.
We have recently completed the installation of the stanchions, windows and hatches, and engines.
Our production team is currently working on the following works: deck hardware (75%), electrical system (60%), plumbing and LPG (60%), steering system (50%), and timber fit-out (25%).






















































































