Deck moved to our Seawind shed on 6th October for the first Assembly stage. Work is being carried out on transom extension. Hull is in our driveway waiting for some Lam parts to be handed over. Deck joining is scheduled for 20th October, 2020.
Production Update – Fit out
We are excited to inform you that your boat is progressing well in the Fit out stage.
We recently finish the life raft box, all deck gear, helm console, coach roof on, steering, and engine put in place.
Our Production team is currently working on plumbing work (70% done), electric work (25%), and timber fitout has started (20%).













Production Update – Fit out
Production Update – Lamination
Production Update – Assembly
Production Update – Assembly
Production Update – Assembly
Production Update – Assembly
Your boat is progressing well in the Assembly stage.
The hull and deck were joined in the last week of May.
Our Production team is currently doing ASSY-2 work, mainly first stage of plumbing, cable and hose conduits, flow-coat work, preparing for deck gear installation, helm seat inserts, and doing hull-deck joint gelcoat repairs.















Production Update – Fit out
We are excited to announce that your boat has been moved to the Fit out stage.
We recently completed the fwd beam and trampoline installation.
Our Production team is working on hull windows, rudder installation, deck gear (25% done), stage-1 electric work, preparing cabin head liners, Laminex bulkheads, and plumbing stage-1.












Production Update – Fit out
It is exciting that your boat has been progressing well in the Fit out stage.
We recently completed the engine installation, forward beam and trampoline.
Our Production team is currently working on composite deck hatches, aircon installation, plumbing (30% done), electric work (40%), continuing engine room fitout.












Production Update – Fit out
It is exciting that your boat is progressing well in the Fit out stage.
We recently completed all deck gear, lifelines, plumbing work, and solar panels.
Our Production team is currently working on electric installation (50% done), timber fitout (75%), steering installation, helm lifting windows, window liners, and plumbing (75%).