Production Update – Assembly 1

Deck moved to our Seawind shed on 6th October for the first Assembly stage. Work is being carried out on transom extension. Hull is in our driveway waiting for some Lam parts to be handed over. Deck joining is scheduled for 20th October, 2020.

Production Update – Completion

We are excited to announce that your boat is now completed and left our factory to the storage yard.

Please see below for some photos of the boat in her final days before being launched. Let us also take you on a tour around your boat via thisĀ Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1170.

Production Update – Lamination

Your boat has made significant progress in the Lamination stage.

At this stage, both hull and deck have been demoulded and they are being completed with some gelcoat works. Currently, our team is also working on the other preparations for deck joining which will take place in the next stage.

Production Update – Fit out

Your boat has been moved to the new stage – Fit out.

At this point, the A-frame, trampoline, and plumbing fittings have been completed. The anchor system and stanchions are both 75% complete. Work is also underway on the deck hardware, electrical systems, and steering, each currently at 25%. Overall, the fit-out is moving forward steadily with key components well in progress.

Production Update – Assembly

We are excited to inform you that your boat has been moved to Assembly stage.

The hull and deck were successfully demolded. Our Lamination team is currently installing the furniture modules inside the hull, while the deck is undergoing trimming and final gelcoat repairs in preparation for the hull-to-deck joining.

Production Update – Assembly

It is exciting that your boat has been moved and progressing well in the Assembly stage.

Our Assembly team is currently completing the final stages of furniture module installation, preparing the hull for the upcoming deck joining. Meanwhile, the Lamination team is carrying out the final gelcoat repairs on the deck to ensure everything is in optimal condition. The joining process is scheduled to take place in the coming days.

Production Update – Assembly

Your boat is progressing well in the Assembly stage.

The hull and deck were joined a while ago. We also completed the installation of thru-hull fittings and tanks recently.
Our Production team is currently working on plumbing and LPG at 15%, and gelcoat repair at 25%.

Production Update – Fit out

It is exciting that your boat has been moved and progressing well in the Fit out stage.

We recently completed the installation of engines, saloon windows, hullside windows, and A-frame. Gelcoat repair is also finished.
Our Production team is currently working on deck hardware, hatches, plumbing, and LPG. Electric system is about 70% of completion.

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

We recently completed the deck hardware on the boat.
Our Production Team is working on electric at 80%, plumbing, LPG at 75%, timber fitout at 70%, steering system at 90%, windows and hatches at 90%.