Deck moved to our Seawind shed on 6th October for the first Assembly stage. Work is being carried out on transom extension. Hull is in our driveway waiting for some Lam parts to be handed over. Deck joining is scheduled for 20th October, 2020.
Production Update – Fit out
Your boat is progressing well in the Fit out stage.
We have recently done with the mast base, deck gear, trampoline, Lewmar hatches, davits, sliding door, fridge and freezer installed (waiting for bench top completion) and washing machine.
Our Production team is currently working on plumbing work (90% done), electric work (75%), timber fitout at 50%.
Production Update – Deck on
It is exciting that your boat has been moved to the Assembly stage.
The boat is currently in assembly 1 deck joining stage by Lamination team. Hull and deck are being well-prepared for joining.
Production Update – Detailing & QA
Production Update – Lamination
Production Update – Lamination
Production Update – Assembly
Production Update – Assembly
Production Update – Assembly
Production Update – Fit out
It is exciting that your boat is taking the first step in the Fit out stage.
We have recently installed engines, fwd beam and trampolines, and solar panels.
Our Production team is currently working on hull and salon windows, forward opening windows, electric installation (25% done), and plumbing work (50%).
Production Update – Fit out
We are excited to inform you that your boat has been moved to the Fit out stage.
We have recently installed all windows, engines, solar panels, composite deck hatches, fwd beam and trampoline.
Our Production team is currently working on remaining deck gear, electric works (50% done), plumbing 75%, and antifouling preparation. Timber fitout has started.