Production Update – Assembly 1

Deck moved to our Seawind shed on 6th October for the first Assembly stage. Work is being carried out on transom extension. Hull is in our driveway waiting for some Lam parts to be handed over. Deck joining is scheduled for 20th October, 2020.

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

We have recently done companionway flooring, plumbing, sliding door and windows. The daggerboards were installed and tested.
Our production team is working on remaining electric installation, timber fitout (75% done), galley bench top, salon ceiling panels. Flexiteek has arrived, ready to apply.

Production Update – Fit out

It is exciting that your boat is taking the first steps in the Fit out stage.

We have recently had engines, forward opening windows, Laminex bulkheads, forward beam and A-frame installed. Lewmar deck hatches were also finished.
Our production team is working on aircon installation, deck gear (50% done), plumbing (25%), and trampoline.

Production Update – Fit out

It is exciting that your boat is progressing well in the Fit out stage.

We have recently had all windows and hatches installed. Aircon, deck gear, composite deck hatches, and antifouling preparation also have been finished.
Our production team is currently working on plumbing (50% done), electric (50%), and timber fitout (25%).

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

We have recently helm seats, all deck gear, and solar panels installed.
Our production team is working on steering, galley fitout, timber fitout (50% done), electric installation (75%), wall and ceiling liners.

Production Update – Fit out

Your boat is progressing well in the last phase of Fit out stage.

We have recently done the solar panels, helm seats, helm windows, interior flooring, galley cabinets, and plumbing.
Our production team is working on steering, wall and ceiling panels, helm displays, electric works (90% done), timber fitout (75%), and nav-desk console.