Deck moved to our Seawind shed on 6th October for the first Assembly stage. Work is being carried out on transom extension. Hull is in our driveway waiting for some Lam parts to be handed over. Deck joining is scheduled for 20th October, 2020.
Production Update – Completion
We are excited to announce that your boat is now completed and left our factory to the storage yard, ready for launching.
Please see below for some photos of the boat in her final days before being launched. Let us also take you on a tour around your boat via this Youtube video.
It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1370.

































































Production Update – Fit out
Production Update – Lamination
Production Update – Lamination
Production Update – Assembly
Production Update – Assembly
Production Update – Assembly
Production Update – Assembly
Production Update – Fit out
We are excited to inform you that your boat has been moved to the Fit out stage.
We recently completed the forward beam, stanchion, and trampoline.
Our Production team is currently working on rudder system, thru-hull fittings (90%), saloon windows (25%), lifelines, deck hardware, steering, and gelcoat repair. Plumbing is about 50% completed.


















Production Update – Fit out
It is exciting that your boat has been progressing well in the Fit out stage.
We recently completed forward beam, A-frame, trampoline, stanchion, thru-hull fittings, hull side windows, and rudder blade.
Our Production team is currently working on anchor system, engines, steering, anchor box, deck hardware, lifelines, plumbing, aircon, heating system, timber fitout, and gelcoat repair.