Your boat is progressing well in Detailing & QA stage.
Currently, the boat is having some engine room components installed and will then be on standby until Torqueedo lithium batteries arrive by sea freight (middle of April).
After that, we plan to have the boat ready for the sea trial in the 2nd week of May.