Your boat has entered the Detailing and QA stage.
Until now, we have done almost main tasks to bring the boat to the final stage such as: anti-fouling, all windows and hatches installed, trampolines, helm station, all interior flooring, galley benchtops, and plumbing.
Currently, we are working on timber fit-out (75%), and electric installations (75%).
Besides, due to the global supply chain issue, there are a few parts coming later than our plan so we truly apologize that the estimated completion date has to be rescheduled to the first week of May. We will keep you posted if there are any changes to this new date.
Thank you for your understanding.