It is exciting that your boat is now in Detailing & QA stage.
We recently completed the jobs of dinghy davits, daggerboard, mast base completion, escape hatches, anchor/windlass assembly, plumbing works, fwd beam, hardtop installation, deck gear installation, aircon installation base, wall and headliners,
Our Production Team is currently working on steering system, deck gear (80%), solar panels, electric installation (70%), timber fitout (70%).