Production Update – Fit out

Your boat has been progressing well in the Fit out stage.

We have completed installing the aft cabin wall and ceiling and bow cabin port side. We also finished the plumbing works, main engine (100%), dinghy davits, escape hatches, daggerboard, anchor/windlass assembly, forward beam, hardtop, wall and headliners installation.

Our Team is currently working on air con (65% at saloon), electric winch, BBQ, gas, compass, installing steering system 50%, solar panels 90%, and deck gear installation (90%)