Production Update – Fit out

Your boat has been progressing well in the first phase of fit-out stage.

We recently completed the jobs of pump, sanitary, thru-hulls, valves, tanks (100%), installing deck equipment (90%), jib track, daggerboard, Port head, and anchor.

Our Production Team is currently working on installing diesel hose, gas pipe, window in 80%, hardtop detailing (90%), helm seat, deck hatches, cross beam, and helm console.