Your boat is progressing well in Fitout stage with some critical parts completed recently.
Based on the team’s updates, the deck-hull exterior joint has been completed and surface preparation is made for gelcoat. All interior laminations before window liners have been completed and backplates have been installed below deck.
At this stage, the team have done some tasks including exhaust system assembly, engine sea water filters, winches, laminated coachroof liner, rudder shaft, surface preparation of fixed window, exterior cockpit step lights and courtesy lights installation.
The production team is currently working on deck gear, stanchions, coachroof, steering system, and interior window liner.