Your boat has been progressing well in the Detailing & QA stage.
Until now, we have done some main tasks to get the boat closer to completion including rudders, gas piping, targa infill, all windows and hatches, all deck gear, lifelines, helm windows, trampoline, and mast base.
We’re currently working on steering, antifouling, plumbing (75% done), electric works (50% done), and shower glass installation.