The current status shows that your boat is progressing well in the Detailing & QA stage.
The boat has recently been equipped with some critical parts to get closer to completion including rudders, antifoul preparation, all windows, all deck gear, aircon unit, freezer, trampoline.
We’re now doing bunk headliners surround, companion way flooring, electric installation (50% done), plumbing near completion, and working on trifold door.