Production Update – Detailing & QA

The Detailing & QA stage is ongoing well, with significant progress made in recent weeks.

At this point, deck gear installations have reached 80% completion, and all deck hatches have been installed. The fresh water plumbing system is 75% complete, while the fuel system plumbing has been entirely finished. Black and grey water plumbing is 65% complete, and the bilge system is fully operational. The installation of wiring and electrical equipment has commenced, and the steering system has been successfully integrated.