Production Update – Detailing & QA

Your boat is currently undergoing the final touches of the Detailing & QA stage, and we are pleased to inform you of some key developments in our recent progress.

At present, deck gear installation is nearly complete, with only the trampolines remaining to be installed. Plumbing systems for fresh, gray, fuel, and bilge water have been fully completed. Electrical and wiring work is over 80% finished. The timberwork is in place, and we’re currently working on the ceiling interior liners and solid wood fiddles. Solar panels have also been installed.

We’re scheduled to apply antifouling to the hull around the end of this month.