Production Update – Detailing & QA

The Detailing & QA stage is ongoing well, with significant progress made in recent weeks.

Up to now, interior and exterior gelcoat repairs have been completed. The black gelcoat on the deck, glass installations, and the coachroof have been completed. Additionally, our team has also finished their works on some other critical parts including bilge system, fuel system, stanchions, all opening deck hatches, deck winches, service & start batteries, charger/Inverter unit, DC/DC chargers, MPPT solar chargers, wiring preparations and cable channels.

We are now working on fresh water system, deck gear installations and timberworks solid wood frames.