Exterior: the daggerboard system is now 100% done. Deck gear, anchor system, longoron and fwd beam works are going well with 80% completed. The installation of cockpit roof is more than half way done. Work is being carried out on the installation of windows and hatches.
Interior: works are being carried out on all cabins – port fwd cabin 85% done, both port and std cabins are more than half way done. Work is now started on the port midship bathroom and in the std main bathroom, the washing machine is now installed. Navigation station is 70% completed and the layout for kitchen cabinet has been put down.
Engineering: engine and fuel system are almost 80% completed.