Your boat is making a significant progress in the new stage – Detailing & QA.
At this point, the stanchion installation has been completed. Progress continues steadily across other systems, with plumbing, deck hardware, and electrical each at 50% completion. Windows and hatches are nearing finalization at 90%, while the steering system has reached 70% completion.