Production update – Detailing & QA

Your boat is currently undergoing the final touches of the Detailing & QA stage, and we are pleased to inform you of some key developments in our recent progress.

At this point, the deck gear installations have been completed and the electrical cabling reaching 85% completion. Timber kit parts installation has also advanced significantly, currently at 90%. Air-conditioning and the LPG system are scheduled to be completed within this week. Looking ahead, electrical and installation tests on the boat, along with the engine start-up, are planned for next week.