Your boat has been progressing well in the Detailing & QA stage, where several additional components have been completed to bring it closer to the final stages.
At this point, we have completed most of critical systems, including the exhaust system, fuel system, bilge system, sea water and black water system.
We are currently working on the freshwater system (90% complete), electrical system (75% complete), and ventilation system, while all timber work installations are 90% complete.