Your boat has been progressing well in the Detailing & QA stage, where several additional components have been completed to bring it closer to the final stages.
At this point, interior gelcoat repairs and glass installation have been completed, along with the installation of the exhaust, fuel, bilge, seawater, and black water systems.
We are currently working on the freshwater system (80% complete), all timberwork installations (40% complete), the electrical system (35% complete), as well as the ventilation and LPG systems.