Your boat is making significant progress in the new stage – Detailing & QA, with 80% of the workload completed.
Recently, some critical components of the boat have been completed, bringing it closer to completion. These include the flooring, port forward cabin, timber fit-out, all interior bulkhead coverings, window liners, headliners, galley area, deck hardware, and stanchions.
We are currently working on the electrical system, plumbing system, navigation system, galley setup, and steering system (85% complete).