INTERIOR
Port water tank installation is 100% done.
Windows liner on both sides are 50% done
Fiberglass windows panels are 100% done
Thru bulkhead access for heater and aircon is 80% done
Next week we will prepare head liner blocks, make provision for wiring harness and under bunk panels.
EXTERIOR
Cockpit gelcoat detailing in cockpit is 70% complete
Hull windows preparation is 100% done
Saloon windows preparation step is done, ready for installing windows.
Deck hatches dry-fitted – 50% complete