The boat is now in her Assembly stage and progressing steadily as scheduled.
Exterior: detailing of cockpit and cutting of access to life raft have now been completed. Works are ongoing for the through holes and detailing of starboard hull.
Interior: there has been quite a milestone achieved with the fitting of bed base cleats, starboard cabin bead base, electrical panels, bulkheads, speaker boxes, holding tanks 100% done. Window liners and bulkheads are more than half way of installation. Kitchen layout is being prepared for the next fitout stage.
Engineer: all tanks have been installed including holding tanks, fuel tanks, and water tanks. Water maker supports are now put in placed. Stanchions installation is 75% completed. More work to be done on the detailing of port and starboard heads.