Production Update – Assembly 2

Deck joining took place in first week of August and the joining process was successful. Inboard engines are planned to arrive at our factory at the beginning of October and will be installed during the first Fitout stage. Lewmar and composite hatches have been installed. We are currently working on rudder installation, flowcoat, chainplates, carpet and bulkhead laminate templates.