The boat has been progressed smoothly with many jobs completed or more than half done.
Exterior work: the installations of transom winches/clutches, transom rub rails and end caps, hatches and windows, compasses, and dinghy davits are 100% completed.
We are currently working on the helm instrument panel, centre boards, targa top, rudders, and antifoul.
Interior: the sliding window and hull side window panels are all in. Roof liners are well underway in all 3 cabins.
Furniture is being fitted in the galley and lounge areas with 80% done. Wardrobe, vanity desk and bathroom vanity are being built. Port and starboard heads are detailed to almost completion.
Plumbing works are almost done including waste plumbing and hot water system. Fresh water system and bathroom plumbing are 80% completed.
Engineering: the installations of exhaust, water maker, battery chargers, fuel system, port and starboard engines are 100% completed.
We are still working on other electrical components, C-zone, steering system, pumps and fuel systems.