Production Update – Lamination

An exciting journey has started. Your boat is making progress in the first stage of production – Lamination.

The hull has just been demolded and the deck is being made in the mold. The coach roof is almost finished in its mold.

Production Update – Assembly

Your boat is progressing well in the second phase of Assembly stage.

Our Production team is working on pluming stage 1 which all thru hulls and water tank installed, conduits and composite small parts installation. The deck has targa bar and roof on.

Production Update – Assembly

Your boat is progressing well in the Assembly stage.

We recently have done the helm pedestals, and first plumbing stage completed. Our Production team is working on center bathroom wall & door frame, and interior composite small parts.

Production Update – Assembly

Your boat is progressing well in the last phase of Assembly stage.

We recently have the engines installed, all plumbing stage 1 works done, and diesel tanks installed.
Our Production Team is currently working on stanchions, pulpits, interior liners, and remaining interior gelcoat repairs.

Production Update – Fit out

It is exciting that your boat has been moved to the Fit out stage.

We recently installed the forward opening windows, and the first plumbing stage was also completed.
Our Production team is working on electric works (20% done), plumbing (50%), wall and headliners, bulkheads and cabin walls Laminex application, and helm windows.

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

Recent jobs that we have completed are all windows and hatches installed, fwd beam, and antifouling preparation.
Our Production team is currently working on plumbing (75% done), steering (75%), deck gear almost completed, timber fitout (30%), and synthetic lifelines.

Production Update – Fit out

Your boat is progressing well in the last phase of Fit out stage.

Recent jobs that we completed are solar panels, trampoline, mast base, all windows, fwd beam, steering, plumbing, aircon.
Our Production team is currently working on deck gear (75% done), electric works (75%), nav station, wall liners, galley fit out (50%).

Production Update – Assembly

Your boat is progressing well in the second phase of Assembly stage.

We recently completed the stanchions, pulpits, and composite chainplates.
Our Production Team is currently working on windows liners, galley base, floor inserts, and composite bunk base.