An exciting journey has started. Your boat is making progress in the first stage of production – Lamination.
Our Lamination team is doing the vacuum infusion in the main hull mold. The team is also laying the fiber inside the deck mold.




Your boat is progressing well in the Assembly stage.
The hull and deck were joined in the last week of May.
Our Production team is currently doing ASSY-2 work, mainly first stage of plumbing, cable and hose conduits, flow-coat work, preparing for deck gear installation, helm seat inserts, and doing hull-deck joint gelcoat repairs.















We are excited to announce that your boat has been moved to the Fit out stage.
We recently completed the fwd beam and trampoline installation.
Our Production team is working on hull windows, rudder installation, deck gear (25% done), stage-1 electric work, preparing cabin head liners, Laminex bulkheads, and plumbing stage-1.












It is exciting that your boat has been progressing well in the Fit out stage.
We recently completed the engine installation, forward beam and trampoline.
Our Production team is currently working on composite deck hatches, aircon installation, plumbing (30% done), electric work (40%), continuing engine room fitout.












It is exciting that your boat is progressing well in the Fit out stage.
We recently completed all deck gear, lifelines, plumbing work, and solar panels.
Our Production team is currently working on electric installation (50% done), timber fitout (75%), steering installation, helm lifting windows, window liners, and plumbing (75%).














Your boat is progressing well in the final phase of fitout stage.
The jobs recently completed are galley fitout, bench top, and interior flooring.
Our Production team is working on antifouling, steering completion, BBQ, electric works (75% done), timber fitout (85% done), nav desk console, and detailing works.