Your boat is progressing well in the Assembly stage.
The hull and deck were joined and Production Team now is installing bulkheads, galley base and tanks inside the boat.














Your boat is progressing well in the Fit out stage.
We have recently finished the dinghy davits, all windows, helm consoles, targa roof, Lewmar and composite deck hatches.
Our Production team is currently working on deck gear (75% done), electric system (50%), plumbing (75%), mast base, and jib track.
Your boat is progressing well in the last phase of Fit out stage.
Some jobs that we have recently completed are sliding door and sliding windows, solar panels, trampoline, forward beam, and washing machine installation.
Our Production team is currently working on electric works (75%), plumbing (90%), timber fitout (75%), remaining steering system and plumbing works, remaining engine room installations, and galley bench top.
Your boat has already entered the new stage after assembly – fitting out.
At this point, we have installed the steering system, all solar panels, all deck gear, flooring and windows. Our team has also done their job on plumbing and antifouling.
Currently, we’re working on electric works (50% done), forward bunk headliners, and trifold doors.
Your boat is progressing well in the Assembly stage.
Your boat has been moved to main production line for assembly 3 stage. Fuel tanks were installed. The deck has targa bar and roof on. Our Production team is working on deck drains, flowcoat works, steering conduits, and small composite parts. Hull-deck join will be started soon.
Your boat is progressing well in the third phase of Assembly stage.
The hull and deck were joined. Some jobs that we have recently done are helm pedestals, plumbing 1st stage completed, centre bathroom wall & door frame, and interior composite small parts. Engines are installed, and all gelcoat repairs done.
Our Production team is currently working on rudder installation, pulpits, and deck gear (winches).