Production Update – Assembly

Your boat is progressing well in the the Assembly stage.

We recently have pulpits and stanchions installed.
Our production team is currently working on hull splashboard, composite window liners, liferaft box, aft bunk composite base, and tanks installation.

Production Update – Fit out

It is exciting that you boat has been moved to Fit out stage.

We recently have all windows installed and completed aft bunk bases, galley base, and thru-hulls.
Our production team is currently working on deck gear (50%), wall liners preparation, and tank installation.

Production Update – Fit out

Your boat has been progressing well in the second phase of Fit out stage.

We recently completed the deck gear, helm seats, fwd beam, hardtop, tanks, and all deck hatches installation.
Our production team is currently working on plumbing 90%, engine room insulation, electric jobs 75% completed, daggerboard installation, early timber fitout.

Production Update – Details & QA

We are excited to inform you that your boat has been moved to Details & QA stage.
We recently finished the dinghy davits, BBQ, cockpit roof, sliding door and sliding glass, galley bench tops, aircon, dagger boards, trampoline, engine room installations, and upholstery.
Our Production team is currently working on electric works (95%), timber fitout at 90%, flexiteek application. Plumbing and electric system testing are about to start.

Production Update – Assembly

It is exciting that your boat is now in the Assembly stage.

The hull was handed over to assembly stage two weeks ago. The deck was finished and has been waiting for being joined to the hull. Our production team is currently installing targa bar, and preparing for hardtop installation.

Production Update – Assembly

Your boat is progressing well in the Assembly stage.

The coach roof has been fully installed on deck.
Our production team is currently doing the dry fitting of deck, and doing trimming together with Lamination. Hull and deck joining will be started soon.

Production Update – Assembly

Your boat is progressing well in the Assembly stage.

We recently finished the installation of engines and fwd opening windows. The plumbing-1 works and helm console with steering tiller were completed.
Our production team is currently working on steering, first stage electric works, pulpits, wall liners preparation, trampoline flange, head liners preparation, interior Laminex panelling.