Your boat has been progressing well in the second phase of assembly stage.
Our Production Team is currently working on the galley base, window liner preparation, composite chainplates, and fitout-1 stage preparation.
Your boat has been progressing well in the second phase of assembly stage.
Our Production Team is currently working on the galley base, window liner preparation, composite chainplates, and fitout-1 stage preparation.
Your boat is progressing well in the Fit out stage.
We recently completed water maker installation, helm console and seats, dinghy davits, sliding door, all windows installed, washing machine in.
Our Production Team is currently working on sail drives installation, deck gear (50% done), plumbing 75%, electric works 30%, headliner, trampoline, and solar panels installation. Timber fitout also has just started.
It is exciting that you boat now is in the Details & QA stage.
We recently completed the antifouling, all plumbing, flexiteek, nav station, galley, interior flooring, aircon, and all deck gear.
Currently remaining works are electric works (90% done) and aft bathroom vanity area. Our Production Team is also doing the checking around the boat to make sure that everything is good before shipping.
Your boat is progressing well in the third phase of Assembly.
We recently completed the center bathroom wall, side windows installed, window liners, coach roof on, helm consoles installed.
Our Production Team is currently working on the antifoul preparation, remaining hull gelcoat repair, trampoline flange. The basic plumbing works have started.
It is exciting that your boat now is taking the first steps in Fit out stage.
We recently completed installing diesel tanks, port side engine, and all window liners done.
Our Production Team is currently working on trampoline flange, helm console, center bathroom wall, basic plumbing, and electric preparation works.
Your boat has been progressing well in the Fit out stage.
We recently completed hull windows installation, engine room fitout, and cabin liner bases.
Our Production Team is currently working on checking all engine electronics, throttle system, preparing deck gear installation, and start of electric installations
Your boat has been progressing well in the Detailing & QA stage.
We have recently done some other main tasks to get the boat closer to completion comprised of antifoul preparation, targa seat, all windows and hatches, all deck gear, all interior flooring, and galley benchtop.
Currently, we’re working on electric installations (75% done), the remaining plumbing (90% done), steering system, freezer, helm seats, and fuel tank installation.