Production Update – Detailing & QA

Your boat has been progressing well in the Detailing & QA stage.

Until now, we have done some main tasks to get the boat closer to completion including all steering, helm stations, all interior flooring, all plumbing, antifouling, and remaining solar panels.

Currently, we’re working on helm seats, electrical parts (75% done), and timber fitout.

Production Update – Fit out

Your boat has been progressing well in the fit out stage.
There are some jobs done on the boat like galley timber fitout, windlass, trampoline, interior flooring, all deck gear, composite deck hatches.
Our Production Team is currently working on: synthetic lifelines, electric works (75% done), cabin timber fitout (75%), plumbing (50%), setting up nav station.

Production Update – Fit out

Your boat has been progressed well in the Fit out stage.

We recently completed remaining hardtop windows and fwd opening windows, trampoline flange, hull gelcoat repairs, deck winches and jammers.
Our Production team is currently working on remaining deck gear, helm console fitout, composite deck hatches, starboarb side interior gelcoat repair, electric works (50%), timber fitout 20%, rudder installation.

Production update – Completion

We are excited to announce that Sweet Disposition is now completed and going to leave our factory for the sea trial.

Please see below for some photos of the boat in her final days before being launched. Let us also take you on a tour around your boat via this YouTube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1170.

Production Update – Lamination

An exciting journey has started. Your boat is making progress in the first stage of production – Lamination.

Up to this point, the side hull and centre hull are already joined. The furniture of the forward cabins and the forward head has been assembled and glassed. Plus, our team has got the omegas glassed as well.

As you can see in the photo, all bulkheads have been manufactured and glassed in their correct locations. According to our team, we plan to place the fuel tanks in their locations and get this job completed within this week. Regarding the centre furniture, at this point, both port head and starboard aft cabin furniture have also been trimmed and we’re going to put them in their locations after some preparations.

Production update – Completion

We are excited to announce that Starlight is now completed and going to leave our factory for the sea trial.

Please see below for some photos of the boat in her final days before being launched. Let us also take you on a tour around your boat via this YouTube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1260.

Production Update – Completion

We are excited to announce that Eora is now completed and left our factory to the port for sea trial.

Please see below for some photos of the boat before being launched. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1370.

Production Update – Lamination

An exciting journey has started. Your boat is making progress in the first stage of production – Lamination.

Our Lamination Team is step by step making the deck in its mold. The hull is being processed the IGU. We plan to demould them soon and Assembly will be started right after that.

Production Update – Assembly

Your boat has been progressing well in the first phase of assembly stage.

The hull and deck were joined and our production team is doing the final preparation inside the boat to get the boat ready for the second phase of assembly stage.