Production Update – Fit out

Your boat is progressing well in the last phase of Fit out stage.

Our Production Team is finalizing timber fitout & upholstery. Electric, plumbing, LPG, timber fitout, navigation instruments are at 95% completed. The boat is scheduled for final quality control, testing, and inspection before shipping soon.

Production Update – Assembly

Your boat has entered the Assembly stage.

Both the hull and deck had finished their journey in Lamination and the deck joining has been completed. We’re now working on bow and transom gelcoat repairs and remaining internal glass works.

Production Update – Fitout

Your boat is now in the Fit-out stage where we have started to work on the key parts and the preparations for windows in.

At this point, the deck joining has taken place, and our team has also completed work on the longeron and gelcoat repairs. We have just started work on deck hardware, windows and hatches, steering, electrical, and plumbing systems.

Production Update – Fitout

Your boat has been progressing well in the fit-out stage and has recently been equipped with several critical components.

At this stage, we have installed the A-frame, forward beam, anchor box, and trampoline. We are currently working on deck hardware (50%), steering (50%), windows and hatches (25%), plumbing (25%), and electrical systems (10%).

Production Update – Detailing & QA

Your boat is progressing well in the Detailing and QA stage.

The boat has recently been equipped with some of the remaining detail parts, bringing it closer to completion. At this stage, the timber fit-out has been completed. The boat is now 95% complete, and we are currently planning for system testing.

Production Update – Completion

We are excited to announce that CHOPSTICKS is now completed and being launched.

Please see below for some photos of the boat in her final days before being launched. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1370.

Production Update – Lamination

An exciting journey has just started. Your boat has been progressing well in our lamination stage.

As you can see in the below photos, some components have already been completed, including the full manufacturing of all furniture, marking a strong foundation for the upcoming phases. Hull lamination is currently ongoing, with deck lamination scheduled to begin later this week. In parallel, the installation of the bulkhead, spider, and omega parts is also underway.

Production update – Assembly

Your boat has now entered the next stage – Assembly, with several major milestones already completed.

Hull lamination, furniture manufacturing, and the installation of the bulkhead, spider, and omega parts are all finished, along with the forward starboard cabins and center furniture installations.

Looking ahead, engine installation is scheduled to be completed this week, followed by the hull and deck joint planned for next week.

Production Update – Assembly

Your boat has been progressing well in the Assembly stage, with the hull and deck joint has been completed.

At this stage, the interior laminations between the hull and deck are now 90% finished, reflecting steady advancement toward the next milestones. Exterior gelcoat repair work is scheduled to begin next week.

Production update – Assembly

Your boat has been progressing well in the Assembly stage.

At this point, the hull and deck laminations have been completed, and the exterior gelcoat repairs are scheduled for completion this week. We are now working on the interior gelcoat repairs.