Production Update – Assembly

Your boat has been progressing well in the second phase of assembly stage.

The jobs that we have recently done are window liners, tank bases, mast base, and stanchions.

Our Production Team is currently working on thru-hulls, galley base, daggerboards, salon ceiling liners, and transom gelcoat repairs.

Production Update – Fit out

Your boat has been progressing well in the first phase of fit-out stage.

We recently completed the jobs of pump, sanitary, thru-hulls, valves, tanks (100%), installing deck equipment (90%), jib track, daggerboard, Port head, and anchor.

Our Production Team is currently working on installing diesel hose, gas pipe, window in 80%, hardtop detailing (90%), helm seat, deck hatches, cross beam, and helm console.

Production Update – Fit out

Your boat has been progressing well in the Fit out stage.

We have completed installing the aft cabin wall and ceiling and bow cabin port side. We also finished the plumbing works, main engine (100%), dinghy davits, escape hatches, daggerboard, anchor/windlass assembly, forward beam, hardtop, wall and headliners installation.

Our Team is currently working on air con (65% at saloon), electric winch, BBQ, gas, compass, installing steering system 50%, solar panels 90%, and deck gear installation (90%)

Production Update – Assembly

Your boat has made some progress in the second phase of assembly stage.

We recently finished the aircon ducting and composite furniture installation. Electric ducting and plumbing conduits were installed. The hull and deck will be planned to be joined soon.

Production Update – Fit out

Your boat is progressing well in the fit-out stage.

We recently completed the cable trays and battery cables. The engines were installed, and so did the salon windows.

Our Production Team is currently working on forward opening windows, cabin liners, and deck gear with 30% done (winch installations). Plumbing has also been started at this stage.

Production Update – Fit out

Your boat is doing well in the second phase of fitting out.

We recently completed the electric cable trays and remaining windows tanks installations. 

Our Production Team is currently working on engine room cabling, plumbing works (30% done), hull gelcoat repairs, wall linter preparation works, and deck winches installation.

Production Update – Fit out

Your boat is progressing well in the fit-out stage over the past few weeks.

We finished the remaining windows, galley raw fitout, and steering completed. Aircon units, fwd beam, mast base, solar panels were installed.

Our Production Team is continuing working on plumbing system and electric system, wall and ceiling liners, trampoline, windlass, composite deck hatches.

Production Update – Details & QA

Your boat is taking the first steps in Details & QA stage.

We have all windows installed, steering, helm consoles, solar panels, fwd beam installed. All deck gear, helm windows, helm seats, steering, galley fitout, BBQ, salon headliners, plumbing were also finished.

Our Production Team is currently working on electric system near final stage, timber fitout (75% done), companion way flooring.