Production Update – Completion

We are excited to announce that Dalliance is now completed and going to leave our factory for the sea trial.

Please see below for some photos of the boat before being launched. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1260.

Production Update – Detailing & QA

Your boat has been going well in the final steps of the Detailing & QA stage.

Since the last update, there are a few parts on the boat that have been recently completed such as all deck gear, A-frame, antifouling, and centre console.

Currently, we’re working on the electric system (50% done), plumbing (50%), and mast compression post.

Production Update – Detailing & QA

Your boat has been progressing well in the final steps of the Detailing & QA stage before it’s completely done.

At this point, the Gori propellers have been installed. Besides, we have also done a few more parts including antifouling, heading system, and solar panels.

Currently, we’re working on electric system (50% done), steering (75%), and interior flooring.

Production Update – Assembly

It is exciting that your boat has been moved to Assembly stage.
We have done the jobs on detailing of the hull. Our Production Team is working on transom hull-deck join glassing, glassing the salon door frame, and nonskid repairs.

Production Update – Assembly

Your boat is taking final steps in the Assembly stage.
We have completed the carbon chainplates, galley base, window composite liners, black paint stb hull, splashboards at inner hulls, and some tanks installed.
Our Production Team is working on the black paint of port hulls, flowcoat works, making the interior floor insert, and continuing with deck gear.

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

We have done with the installation of cockpit hardtop, helm consoles, and aft bunk bases.
Our Production Team is currently working on the deck gear (60%), inside fairing of daggerboard casing, interior wall liners, electric installations (30%), floor inserts, plumbing (75%), and salon headliners.

Production Update – Fit out

You boat is progressing well in the Fit out stage.

We have done the tasks of deck non-skid, mast base, deck hatches, solar panels, interior headliners preparation, and galley furniture. The companionway flooring, heating system, deck gear, composite deck hatches, trampoline and BBQ have also been completed.

Our production team is currently working on the steering system, the aircon, timber fitout (50%), electric system (50%), starboard aft bunk, and cabin healiners. Last late parts are estimated to arrive until last week of September and first week of October for installation.

Production Update – Assembly

Your boat has made some progress in Assembly stage.

We already installed the aircon ducting, windows liners and water tank . Both port and starboard aft furniture were installed. The boat will be moved to main production line for hull and deck joining soon.

Production Update – Assembly

It is exciting that your boat has been moved to Assembly stage.

Our Production Team is working on port and starboard side aft furniture installation, and aircon ducting inside the hull. The deck is also finished and waiting to be joined with the hull soon.