Production Update – Fit out

Your boat has made significant progress in Fit out stage.

We have done with window glass and hatches installation, hull gelcoat repairs, steering column and steering equipment, cabin bunk frames, plumbing (75%), longeron.
Our production team is working on the preparation for wall and headliners installation, deck gear (50%), installing remaining tankage.

Production Update – Fit out

Your boat has made significant progress in Fit out stage.
Our Production Team are finishing step by step the electric works (75% done), the plumbing works (75% done). We are now focusing on the timber kit installation to get the boat well-timbered finished.

Production Update – Lamination

Your boat has made significant progress in Lamination stage.

The hull was demolded and our Lamination Team is working on trimming jobs around the hull. Composite furniture parts are being finished to get ready for being installed in the hull.

Production Update – Assembly

We are excited to inform you that your boat is now in Assembly stage.
All of the furniture parts were installed inside the hull. The deck is finished waiting to be joined with the hull. Its hardtop is being finished, then it will be joined with the deck soon. We have a hull-deck joining plan at the end of next week. 

Production Update – Assembly

Your boat has made some progress in Assembly stage.

We have done with hull-deck joining, and the coach roof and targa bar were on. Our Production Team is currently working on transom deck joining gelcoat repairs, antifouling preparation, and flow coat works.

Production Update – Fit out

It is exciting that your boat has taken first steps in Fit out stage.

We have done with the trampoline flanges, window liners, flowcoat works, and antifoul preparation.
Our Production Team is currently working on installing interior composite parts, saloon window frames, plumbing. Deck gear installation has also been started.

Production Update – Fit out

Your boat has made some progress in Fit out stage.

We have done with coach roof and targa bar gelcoat repairs, engine installation as well.
Our team is currently working on the electric cable trays, deck gear, interior gelcoat repairs, trampoline flanges, helm seats, forward opening windows, and plumbing works.

Production Update – Fit out

Your boat has made some progress in Fit out stage.
We have done the with the antifouling and all windows installed.
Our production team is currently working on rudder installation, plumbing, engine room installations, electric system (50% done), deck gear (50% done).

Production Update – Fit out

Your boat has made some progress in Fit out Stage.

We have done with all windows and hatches, BBQ, aircon systems, deck gear, and trampolines.
Our team is currently working on the electric system (75% done), wall liners, headliners, plumbing (75% done). Timber fitout preparation is being processed.