We are excited to inform you that your boat has just been moved to Assembly stage.
Our Lamination team is doing first steps of main furniture assemble inside the hull. Besides, the deck will be started soon.





Your boat is progressing well in the Assembly stage.
We recently finished the installation of engines and fwd opening windows. The plumbing-1 works and helm console with steering tiller were completed.
Our production team is currently working on steering, first stage electric works, pulpits, wall liners preparation, trampoline flange, head liners preparation, interior Laminex panelling.
Your boat has been progressing well in the Fit out stage.
At this point, a few more detailed components have been finished including solar panels, helm seats, steering, galley bench tops, hydronic heating system, trampoline, companionway floorings, all hatches and windows.
Our production team is now working on deck gear (75% done), electric (25%), plumbing (75%), and bunk headliners.
Your boat has been progressing well in the last phase of Fit out stage
We recently completed composite deck hatches, plumbing, salon flooring, aircon, trampoline, and all deck gear.
Our production team is currently working on galley fitout (75%), timber fitout (75%), companionway flooring, helm and dashboard electronics, and electric windows.
We are excited to announce that your boat is now completed and will be wrapped up soon to move to the storage yard.
Please see below for some photos of the boat in her final days before being wrapped up. Let us also take you on a tour around your boat via this Youtube video.
Kindly be informed that the BBQ may not be seen in this video as it will arrive at the factory within the next two days. Therefore, we will send you photos in another email after the BBQ is installed.
It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1370.