Production Update – Assembly

Your boat is progressing well in the Assembly stage.

We recently have completed pulpit, longeron, and first stage of plumbing (thru-hulls, main hoses).
Our Production team is currently working on deck gear including winches, chainplates, Laminex bulkheads, window liners and hull windows.

Production Update – Fit out

It is exciting that your boat is taking the first step in the Fit out stage.

We have recently installed engines, fwd beam and trampolines, and solar panels.
Our Production team is currently working on hull and salon windows, forward opening windows, electric installation (25% done), and plumbing work (50%).

Production Update – Fit out

We are excited to inform you that your boat has been moved to the Fit out stage.

We have recently installed all windows, engines, solar panels, composite deck hatches, fwd beam and trampoline.
Our Production team is currently working on remaining deck gear, electric works (50% done), plumbing 75%, and antifouling preparation. Timber fitout has started.

Production Update – Fit out

It is exciting that your boat is progressing well in the Fit out stage.

We have recently finished all deck gear, plumbing, Lewmar hatches, windlass, solar panels installation, trampoline, and all windows.
Production Team is currently working on steering system (50% done), helm station fitout, electric work (75%), timber fitout 50%, and interior flooring.

Production Update – Fit out

Your boat is progressing well in the last phase of Fit out stage.

We have recently done with interior floorings, galley timber and bench top, plumbing work, and all deck gear done.
Our Production team is currently working on electric work (95% done), interior liners, remaining steering work, and timber fitout 75% completed. Deck organizer and induction stove are coming in final stage.

Production Update – Detailing & QA

It is exciting that your boat is now in the detailing & QA stage.

The boat is entering the final stage. Remaining works are ceiling liners of salon and cabins, and detailing works. Production team will do the system testing (plumbing, electric, engines) in the next two weeks.

Production Update – Completion

We are excited to announce that Danielle is now completed and left our factory to the port for launching.

Please see below for some photos of the boat in her final days before being launched. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1370.

Production Update – Completion

We are excited to announce that No More Tears is now completed and left our factory to the port for launching.

Please see below for some photos of the boat in her final days before being launched. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1370.

Production Update – Assembly

An exciting journey has started. Your boat is making progress in the first stage of production – Lamination.
The hull and deck were demolded and our Lamination Team is doing the trimming. The coach roof is also being made in the mold.