It is exciting that your boat has been moved to Assembly stage.
The hull and deck are finished and ready to be joined at the moment. The joining is planned to be done this week.






Your boat is progressing well in the Assembly stage.
The hull and deck were joined in the last week of May.
Our Production team is currently doing ASSY-2 work, mainly first stage of plumbing, cable and hose conduits, flow-coat work, preparing for deck gear installation, helm seat inserts, and doing hull-deck joint gelcoat repairs.
We are excited to announce that your boat has been moved to the Fit out stage.
We recently completed the fwd beam and trampoline installation.
Our Production team is working on hull windows, rudder installation, deck gear (25% done), stage-1 electric work, preparing cabin head liners, Laminex bulkheads, and plumbing stage-1.
It is exciting that your boat has been progressing well in the Fit out stage.
We recently completed the engine installation, forward beam and trampoline.
Our Production team is currently working on composite deck hatches, aircon installation, plumbing (30% done), electric work (40%), continuing engine room fitout.
It is exciting that your boat is progressing well in the Fit out stage.
We recently completed all deck gear, lifelines, plumbing work, and solar panels.
Our Production team is currently working on electric installation (50% done), timber fitout (75%), steering installation, helm lifting windows, window liners, and plumbing (75%).
Your boat is progressing well in the final phase of fitout stage.
The jobs recently completed are galley fitout, bench top, and interior flooring.
Our Production team is working on antifouling, steering completion, BBQ, electric works (75% done), timber fitout (85% done), nav desk console, and detailing works.
We are excited to announce that PALARRAN is now completed and left our factory to the storage yard, ready for launching.
Please see below for some photos of the boat in her final days before being launched. Let us also take you on a tour around your boat via this Youtube video.
It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1370.
An exciting journey has just started. Your boat has been progressing well in our Lamination stage.
Currently, we are working on the hull and deck gelcoat preparation. The targa bar has been installed, and the targa roof installation is in progress. Once both the deck and hull are completed, they will move on to the next step: deck joining.
Your boat has already entered the new stage after lamination – Assembly.
At this point, all ASSY-1 deck joining and internal glassing works have been completed, which allowed the boat to be moved to the ASSY-2 stage on June 2nd, with the rudders already installed. We are now working on the plumbing system.