Your boat has entered the Detailing and QA stage.
Until now, we have done many main tasks to complete the boat including antifouling, all windows installation, deck hatches, deck gear, all interior flooring, plumbing, galley benchtops, stove & oven, forward bunk headliners, solar panels and cookout BBQ.
Currently, we are doing timber fit out, steering system, and electric installations (75%).
However, due to the global supply chain issue, we have quite a few missing parts that either pending for delivery date from the supplier or arrived later than we planned. We currently reschedule the completion date for your hull on the last week of April but we will keep you updated if there are any changes to this schedule.