Jobs have been completed on deck gear, hardtop nonskid repair, trifold door, engines, Sado glass, and floors. Electric system is 75% done; interior timber, steps, plumbing have been progressed to 50% of completion. Boat is well on schedule.
Production Update – Fitout 2
Tremendous progress has been achieved in the past month.
Interior: all tanks installation has been completed. Kitchen is almost done with all shelves, bench top, utilities installed. Electrical panel and Navigation desk are 100% done. Bed bases are completed including interior furniture. We are working on final detailing of bathrooms and running of electrical wiring.
Exterior: we have made quite a progress with the completion of starboard hull detailing, cockpit detailing, through holes and life raft access.
Engineering: watermaker supports, holding tanks, water tanks, fuel tanks, pre-fit stanchions, and galley kick are now completed.