Production Update – Completion

We are excited to announce that your boat is now completed and will be wrapped up soon to move to the storage yard.

Please see below for some photos of the boat in her final days before being wrapped up. Let us also take you on a tour around your boat via this Youtube video

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1370.

Production Update – Detailing & QA

SanJe is progressing well in the Detailing & QA stage.

At this point, your boat has basically been completed. After the lithium batteries arrive, it will be able to commission all the systems.

We genuinely apologize for any inconvenience this delay may cause and will keep you updated via the walk-thru video when the boat is completed.

Production Update – Assembly

Your boat is taking the final steps in Assembly stage.

We have recently finished the engine room preparation, galley base, and flowcoat works.
Our Production team is currently working on deck gear preparation works, fitting dagger boards, and thru-hulls.

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

We have recently finished the dinghy davits, all windows, helm consoles, targa roof, Lewmar and composite deck hatches.
Our Production team is currently working on deck gear (75% done), electric system (50%), plumbing (75%), mast base, and jib track.

Production Update – Fit out

Your boat is progressing well in the last phase of Fit out stage.

Some jobs that we have recently completed are sliding door and sliding windows, solar panels, trampoline, forward beam, and washing machine installation.
Our Production team is currently working on electric works (75%), plumbing (90%), timber fitout (75%), remaining steering system and plumbing works, remaining engine room installations, and galley bench top.

Production Update – Fit out

Your boat has already entered the new stage after assembly – fitting out.

At this point, we have installed the steering system, all solar panels, all deck gear, flooring and windows. Our team has also done their job on plumbing and antifouling.

Currently, we’re working on electric works (50% done), forward bunk headliners, and trifold doors.

Production Update – Lamination

An exciting journey has started. Your boat is making progress in the first stage of production – Lamination.
The hull has just been demolded and moved to Assembly 1. The deck is finished and will be demolded soon. The coach roof is almost finished in its mold.