Production Update – Assembly

Your boat is progressing well in the Assembly stage.

Your boat has been moved to main production line for assembly 3 stage. Fuel tanks were installed. The deck has targa bar and roof on. Our Production team is working on deck drains, flowcoat works, steering conduits, and small composite parts. Hull-deck join will be started soon.

Production Update – Assembly

Your boat is progressing well in the third phase of Assembly stage.

The hull and deck were joined. Some jobs that we have recently done are helm pedestals, plumbing 1st stage completed, centre bathroom wall & door frame, and interior composite small parts. Engines are installed, and all gelcoat repairs done.
Our Production team is currently working on rudder installation, pulpits, and deck gear (winches).

Production Update – Fit out

It is exciting that your boat has been moved to the Fit out stage.

Some jobs that we have recently done are engines installed, windlass, forward beam, plumbing stage-1 completed.
Our Production team is working on deck gear (winches), starting electric first stage, and solar panels installation.

Production Update – Fit out

It is exciting that your boat has been moved to the Fit out stage.

We have recently done the forward beam, trampoline, and aircon installation.
Our Production team is currently working on steering (50% done), preparing windows installation, electric works (50%), window liners, plumbing works (75%), and laminex bulkheads.

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

Some jobs that we have recently completed are aircons, all windows, solar panels, all deck gear, trampoline, fwd beam, and windlass.
Our Production team is currently working on electric works (50%), plumbing (90%), steering (75%), galley fitout, timber fitout (50%), composite deck hatches, mast base, and helm windows.

Production Update – Fit out

Your boat is progressing well in the last phase of Fit out stage.

Some jobs we have recently done are antifouling, steering, helm station electronics, engine controls, all plumbing, all deck gear, and helm seats.
Our Production team is currently working on timber fitout (75%), electric installations (90%), interior flooring, wall liners, upholstery.

Production Update – Completion

We are excited to announce that Psipsina is now completed and left our factory to the storage yard.

Please see below for some photos of the boat in her final days before being shipped. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1160 Lite.

Production Update – Assembly

Since the last update, your boat has already entered the new stage – Assembly.

Until now, the hull and all furniture have been infused. Omega supports, all inner bulkheads, forward cabins, and starboard forward head furniture have been glassed.

In the meantime, the hull has been demoulded and we have also completed some other parts including the forward main bulkhead, hull bottom flowcoat application, and fuel tank assembly.

Currently, we’re working on the centre furniture assembly.

Production Update – Completion

We are excited to announce that Flying Tiger is now completed and will be wrapped up soon for shipping.

Please see below for some photos of the boat in her final days before being shipped. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1600.

Production Update – Detailing & QA

The current status shows that your boat is progressing well in the Detailing & QA stage.

At this point, targa and coachroof have been assembled and glassed. Gelcoat repairs of targa have been completed 80%.

The boat has recently been equipped with some critical parts to get closer to completion such as side hull windows, deck upper windows, front opening hatches, wiring and installation for the main power system ( Lithium batteries, DC/DC chargers, MPPTs, Charger/Inverter, Czone etc). Also, the bowspirit infrastructure has been completed and tested for bowspirit fitting. Frames for ceiling liner-upholstery installation have been manufactured and glassed.

Currently, the team is working on deck gear installations, all stanchions, deck fillers, windlass, exterior gelcoat works (70% done), fuel system plumbing, black water system plumbing, and preparation for timberworks. The upholstery kit production is due to start in week 20.