Your boat is progressing well in the Assembly stage.
Hull and deck were joined together. Our Production Team is working on the gelcoat repair around the boat. First stage of plumbing tasks will be started soon.













It is exciting that your boat has been moved to the Fit out stage.
We have recently installed engines, forward opening windows, Laminex bulkheads, forward beam and A-frame, and Lewmar deck hatches.
Our Production team is working on aircon installation, deck gear (50% done), plumbing (25%), and trampoline.
Your boat is progressing well in the last phase of Fit out stage.
We have recently completed solar panels, helm seats, helm windows, interior flooring, galley cabinets, and plumbing.
Our Production team is working on steering, wall and ceiling panels, helm displays, electric works (90% done), timber fitout (75%), and nav-desk console.
We are excited to announce that your boat is now completed and left our factory to the storage yard.
Please see below for some photos of the boat in her final days before being launched. Let us also take you on a tour around your boat via this Youtube video.
It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1370.
Your boat is progressing well in the Fit out stage.
We have recently done companionway flooring, plumbing, sliding door and windows. The daggerboards were installed and tested.
Our production team is working on remaining electric installation, timber fitout (75% done), galley bench top, salon ceiling panels. Flexiteek has arrived, ready to apply.