Congratulations – Sea Moon is on her way!

Your Seawind 1160 Lite has been completed, and is on her way to you. A quick tour of the boat can be viewed via this Youtube video. Sea Moon is going to be arrived at Brisbane on 15th of December, 2020.

It has been a pleasure building this boat for you and on behalf of the entire team at Seawind Catamarans we wish you many years of fun filled enjoyment aboard your new Seawind 1160 Lite.

Fair winds and following seas,

Production Update – Fitout 2

Jobs have been completed on deck gear, hardtop nonskid repair, trifold door, engines, Sado glass, and floors. Electric system is 75% done; interior timber, steps, plumbing have been progressed to 50% of completion. Boat is well on schedule.

Production Update – Fitout

The boat has entered her first Fitout stage. All hatches, window liners, trampoline are installed on the boat. Works are being carried out on trifold door, trims for cabin headliners, electric works and deck gear. The boat is on schedule.

Production Update – Assembly

Deck joining took place on time at 6th July and the joining was successfully done. All Assembly 1 works are now done, plus trampoline has been installed. We are currently working on window liners, carpet works, and Lewmar deck hatches. The boat is on schedule.

Production Update – Assembly

Deck handover was done on 26th June, and the boat is now at our Assembly 1 station. Hull was delivered to the Seawind shed on 2nd July. Targa bar and targa roof were installed by the first week of July. Stanchions are installed and painting the blacks is being prepared. Deck joining was started on 6th July and is now well underway.

Production Update – Lamination

Construction is now started on the boat. Hull is at its final stage of IGU and work is started on gelcoat of the furniture. Deck is completed with its Lamination and is waiting to be moved to our Seawind shed for the joining process.