Production Update – Completion

We are excited to announce that Mavi Kedi has been completed and is ready to be delivered.

Please see below for some photos of the boat in her final days before being wrapped up. Let us also take you on a tour around your boat via this video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1260.

Production Update – Fit out 2

Your boat is now at the second phase of fitting out

At this point, we have done with antifoul preparation, all deck gear, helm windows, and forward bunk liners. All interior flooring has also been completed.

Currently, we are completing the remaining window glass installations, electric work is 75% done. 80% of plumbing jobs and timber outfitting have also been carried out.

Production Update – Fit out 1

Your boat has now moved to a new stage – fitting out.

At this stage, we have the rudders and steering system installed, Lewmar hatches in place, galley benchtops, and window liners. We have also had the BBQ fitted, all plumbing has been done, as well as forward opening windows installation.

Currently, we are 80% done with the deck gear and 30% done with electric installations. Helm seats have been installed, as well as the interior flooring.

Production Update – Assembly 2

Your boat has been progressing well in the second phase of assembly.

After the hull and deck arrived at Seawind shed, the deck joining took place on November 18.

We are now working on thru-hulls, Lewmar hatch installation, and steering installation. Plumbing work has also started.

Production Update – Assembly 1

We have made significant progress with your boat in our facility since the last production update.

Both hull and deck were delivered to our Seawind shed after finishing final works in lamination.

We are now detailing the hull and deck getting them ready for the assembly stage.

Production Update – Lamination

It has been quite some time since we last updated you on the status of your boat in the Seawind factory. Although we have been working with a small team during the lockdown period, your boat has been making progress in this lamination stage.

We are now working on gelcoat repairing for the deck and will start IGU for the hull next week.

Production Update – Lamination

An exciting journey has just started. Your boat is now at her very first stage of the production – lamination.

The construction has just been started on the deck. We are laying up fiber and getting to inner skin layers ready for infusion. The hull is expected to be under construction this week.