Production Update – Detailing & QA

Your boat is progressing well in Detailing & QA stage.

Currently, the boat is having some engine room components installed and will then be on standby until Torqueedo lithium batteries arrive by sea freight (middle of April).
After that, we plan to have the boat ready for the sea trial in the 2nd week of May.

Production Update – Detailing & QA

The boat is now at the driveway of the potential final stage.

At this point, we are still waiting for the electric propulsion parts so the electric installations are temporarily stalled.

In the next two weeks, when the electric propulsion parts and genset arrive, we will install them and let the boat go through the remaining steps to be completed.

Production Update – Assembly

Your boat is progressing well in the assembly stage.

After the handover from the Lamination team on September 15, the deck and hull were joined on September 21.

Currently, we are working on the internal deck joint glass works and preparing for Targa bench installation.

Production Update – Lamination

An exciting journey has started. Your boat is making progress in the first stage of production – lamination.

Both hull and deck were demoulded and we are doing the final touches before moving them to Seawind shed for assembly next week.