Production Update – Detailing & QA

It is so excited that your boat has reached the Detailing & QA stage.

We are currently working on cabins and saloon fitout with 50% done, electric and plumbing 75% completed. Navigation desk dashboard is about to be installed. Trifold door and deck nonskid repair have been done. Our 1370 team is waiting to have final timber fitout being provided to install. Upholstery was also completed.

Production Update – Fit out

Your boat has some significant progress in Fit out stage.

All windows, deck gear and water maker were installed, and currently the team is preparing for timber kits installation.

Our team now is also working on electric installations with seventy five percent done, plumbing with fifty percent done and remaining deck gear which is almost completed. With this progress, the boat will reach the completion stage soon.

Production Update – Fit out

Your boat is progressing well in the first phase of fitting out.

At this point, the steering has been completed and we are working on windows installation, Lewmar hatches, antifouling, electric installations (50%), engine room fitout, and deck gear (50%). Also, we are preparing for timber kit installations.

Production Update – Lamination

We have completed the hull infusion and joining of the outboard hulls and have now started working on the stringers/grids plug, which is being constructed inside your hull to ensure the perfect fit.

We have another 10 days of work on this plug before we can pull a mold and then continue with the build of your hull, gluing in the newly formed grids, glassing in the bulkheads, and then demolding.