Production Update – Details & QA

Your boat is now in the Details & QA stage.

We have done the tasks of steering, engine room installations, all main electric works, windows, hatches, plumbing, deck gear, solar panels, and helm windows.
Our Production Team is currently working on timber fitout (75% done), plumbing 80% and upholstery. Helm and nav desk electronics, remaining interior flooring, detailing works have been progressed well.

Production Update – Fit out

Your boat is taking the final steps in Fit out stage.

We have done with the steering, engine room installations, all main electric works, windows, hatches, plumbing, deck gear, solar panels, and helm windows.
Our team is currently working on timber fitout, installing escape hatches, companionway steps, window and wall liners, trampolines, and upholstery. We will soon start with helm and nav desk electronics.

Production Update – Fit out

Your boat has made some significant progress in Fit out stage.

Our production team have been done with the steering system, all windows including helm windows, deck gear, and Lewmar hatches. We are currently working on electric works (75%), plumbing (75% done), helm window, galley raw fitout, timber bulkheads, bunk raw fitout, solar panels and headliner.

Production Update – Fit out

It is great that your boat has some significant progress in Fit out stage.

All hardtop windows were installed, and the steering system was also done. Our team now is is preparing for furniture installation. They are also working on laminate bulkheads, electric works with fifty percent done, plumbing with around thirty percent in progress and doing remaining hull windows.

Production Update – Fit out

Your boat is progressing well in the first phase of fitting out.

At this point, we have done with the hardtop installation, trampoline flange, window liners, antifoul preparation, and battery cables. In addition, the engines were also installed.

Now, we are working on deck gear, interior composite parts and plumbing. All windows will be installed by 10th of March as per our plan.

Production Update – Assembly

Your boat is now in the second phase of Assembly.

In the last two weeks, we had managed to get all 4 large pieces of the interior in place, glued and tapped in. At the same time, the freshwater tank had been installed successfully.

In the next few weeks, the main deck will be demolded and joined, which is another major milestone in the construction process.