Your boat is taking the final steps to completion.
Our Team now is working on the repairs and some final modifications to make sure that the boat is coming to you in best appearance.
Your boat is taking the final steps to completion.
Our Team now is working on the repairs and some final modifications to make sure that the boat is coming to you in best appearance.
Your boat is now in the Details & QA stage.
We have done the tasks of steering, engine room installations, all main electric works, windows, hatches, plumbing, deck gear, solar panels, and helm windows.
Our Production Team is currently working on timber fitout (75% done), plumbing 80% and upholstery. Helm and nav desk electronics, remaining interior flooring, detailing works have been progressed well.
Your boat is taking the final steps in Fit out stage.
We have done with the steering, engine room installations, all main electric works, windows, hatches, plumbing, deck gear, solar panels, and helm windows.
Our team is currently working on timber fitout, installing escape hatches, companionway steps, window and wall liners, trampolines, and upholstery. We will soon start with helm and nav desk electronics.
Your boat has made some significant progress in Fit out stage.
Our production team have been done with the steering system, all windows including helm windows, deck gear, and Lewmar hatches. We are currently working on electric works (75%), plumbing (75% done), helm window, galley raw fitout, timber bulkheads, bunk raw fitout, solar panels and headliner.
It is great that your boat has some significant progress in Fit out stage.
All hardtop windows were installed, and the steering system was also done. Our team now is is preparing for furniture installation. They are also working on laminate bulkheads, electric works with fifty percent done, plumbing with around thirty percent in progress and doing remaining hull windows.
Your boat is progressing well in the first phase of fitting out.
At this point, we have done with the hardtop installation, trampoline flange, window liners, antifoul preparation, and battery cables. In addition, the engines were also installed.
Now, we are working on deck gear, interior composite parts and plumbing. All windows will be installed by 10th of March as per our plan.
Your boat is now in the second phase of Assembly.
In the last two weeks, we had managed to get all 4 large pieces of the interior in place, glued and tapped in. At the same time, the freshwater tank had been installed successfully.
In the next few weeks, the main deck will be demolded and joined, which is another major milestone in the construction process.