Production Update – Details & QA

It is exciting that your boat now is in the Details & QA stage.

We recently completed: all interior flooring, timber fitout, galley benchtop and equipment.
Our Production team is working on: chart plotters installation, upholstery, testing plumbing and electric system, completing navigation console, doing detailing works.

Production Update – Fit out

Your boat has been progressing well in the last phase of Fit out stage

We recently completed composite deck hatches, plumbing, salon flooring, aircon, trampoline, and all deck gear.
Our production team is currently working on galley fitout (75%), timber fitout (75%), companionway flooring, helm and dashboard electronics, and electric windows.

Production Update – Fit out

Your boat has been progressing well in the Fit out stage.

We recently completed hull windows installation, engine room fitout, cabin liner bases, water maker installed, composite helm stations, antifouling preparation.
Our production team is currently working on steering system (75% done), hull windows, plumbing 30%, deck gear, windlass, starting with hardtop windows. Port side gelcoat repair is also being processed, and next week starting with stb side. Gelcoat repairs are on track. Timber fitout is about to start for port side.

Production Update – Fit out

Your boat has been progressing well in the Fit out stage.

We recently completed hull windows installation, engine room fitout, and cabin liner bases.
Our Production Team is currently working on checking all engine electronics, throttle system, preparing deck gear installation, and start of electric installations

Production Update – Fit out

Your boat is progressing well in the fit-out stage.

We recently completed the cable trays and battery cables. The engines were installed, and so did the salon windows.

Our Production Team is currently working on forward opening windows, cabin liners, and deck gear with 30% done (winch installations). Plumbing has also been started at this stage.

Production Update – Fit out

Your boat is taking the first steps in Fit out Stage.

The stanchions and pulpit were installed on the boat. Our Production Team is currently working on the liferaft box, installing tanks, hoses and ducts, interior gelcoat repairs, targa and coach roof gelcoat repairs.

Production Update – Assembly

Your boat is taking final steps in the Assembly stage

We have the flowcoat works completed. Our Production Team is currently working on trampoline flange, pulpit and stanchion installation, and targa bar liner. First plumbing tasks are completed.

Production Update – Assembly

Your boat has made some progress in Assembly stage.

We have done with hull-deck joining, and the coach roof and targa bar were on. Our Production Team is currently working on transom deck joining gelcoat repairs, antifouling preparation, and flow coat works.

Production Update – Assembly

Your boat has made some progress in Assembly stage.

The boat was moved over to 1370 main production line. Our production team is preparing the interior to get the hull be ready for joining in the next couples of weeks. The gelcoat surface on the bottom of the boat is also being finished.

Production Update – Assembly

Your boat is making some progress in Assembly stage.

Our production team is doing the hull gelcoat repair to ensure the best skin of the boat before moving to joining stage. The team is also working on the small furniture inside the hull. The deck is finished and ready to be joined with the hull.