Production Update – Fit out

Your boat is progressing well in the second phase of Fit out stage.

We recently have trampoline installed, and all windows fully completed.
Our Production team is currently working on remaining engine room fitout, electric work (75% done), timber fitout (35%), remaining steering installation, and plumbing (75%).

Production Update – Fit out

It is exciting that your boat has been moved to Fit out stage.

We recently completed the plumbing first stage and aircon units installed. Chainplates, Laminex bulkheads, windlass, forward beam and A-frame were also installed.
Our production team is currently working on rudder installation and steering, deck gear (winches), stage-1 electric works, windows and wall liners, and trampoline.

Production Update – Assembly

Your boat is progressing well in the third phase of Assembly stage.

The hull and deck were joined. Some jobs that we have recently done are helm pedestals, plumbing 1st stage completed, centre bathroom wall & door frame, and interior composite small parts. Engines are installed, and all gelcoat repairs done.
Our Production team is currently working on rudder installation, pulpits, and deck gear (winches).

Production Update – Assembly

Your boat is progressing well in the second phase of Assembly stage.

Our Production team is working on pluming stage 1 which all thru hulls and water tank installed, conduits and composite small parts installation. The deck has targa bar and roof on.

Production Update – Assembly

It is exciting that your boat has taken the first steps in Assembly stage.

The hull was demolded and Lamination Team is doing the Assembly 1 with furniture installed. The coach roof was also finished and ready for joining to the deck. The deck will be demolded soon, preparing for hull-deck join.