Production Update – Completion

We are excited to announce that Zephyr is now completed and left our factory to the storage yard for shipping.

Please see below for some photos of the boat in her final days before being shipped. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1370.

Production Update – Fit out

Your boat is progressing well in the last phase of Fit out stage.

We have recently done with interior floorings, galley timber and bench top, plumbing work, and all deck gear done.
Our Production team is currently working on electric work (95% done), interior liners, remaining steering work, and timber fitout 75% completed. Deck organizer and induction stove are coming in final stage.

Production Update – Fit out

It is exciting that your boat has been moved to the Fit out stage.

We have recently done forward beam installation, trampoline, engines, hull windows, washing machine, aircon, and Laminex bulkheads.
Our production team is currently working on antifouling preparation, electric work (35% done), plumbing (75%), deck gear (75%), and rudder installation.

Production Update – Assembly

Your boat is progressing well in the last phase of Assembly stage.

Deck joining internal glass work was completed.

Our Production team is currently working on salon windows cutouts, hull windows, push and pulpits, installing AC units, applying Laminex bulkhead panels. The first stage of plumbing work is ongoing.