Production Update – Fit out

It is exciting that your boat is progressing well in the Fit out stage.

We recently have flooring, stanchion, A-frame, and all windows installed.

Our Production team is working on antifouling, lifelines, and anchor box. Deck gear is 85% completed. Engine, steering, and electric work are at 90% completed. Timber fitout & plumbing are about 80% completed.

Production Update – Fit out

We are excited to announce that your boat has been moved to the Fit out stage.

We recently completed the fwd beam and trampoline installation.
Our Production team is working on hull windows, rudder installation, deck gear (25% done), stage-1 electric work, preparing cabin head liners, Laminex bulkheads, and plumbing stage-1.

Production Update – Assembly

We are excited to inform you that your boat is now in Assembly stage.

The deck was demolded and has coach roof installed. Our Assembly team is doing Assembly 2 works inside the hull, mainly first plumbing stage, cable and hose conduits, and preparing for deck joining.