Production Update – Completion

We are excited to announce that MAVERICK is now completed and moved to the storage yard, ready for launching.

Please see below for some photos of the boat in her final days before being launched. Let us also take you on a tour around your boat via this Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1370.

Production Update – Fit out

Your boat is progressing well in the Fit out stage.

We recently completed the deck hardware, stanchion, windows & hatches, A-frame, trampoline & anchor box.

Our Production team is currently working on steering (85%), electric (80%), plumbing & LPG (85%), timber fitout (80%) and solar panels 80%.

Production Update – Fit out

We are excited to inform you that your boat has been moved to the Fit out stage.

We recently completed the forward beam, stanchion, and trampoline.

Our Production team is currently working on rudder system, thru-hull fittings (90%), saloon windows (25%), lifelines, deck hardware, steering, and gelcoat repair. Plumbing is about 50% completed.

Production Update – Lamination

An exciting journey has started. Your boat is making progress in the first stage of production – Lamination.

The hull has been finished and just been demolded. The deck is also completed and will be demolded soon in the next couples of days. Our Lamination team is preparing to make the coach roof soon.