Production Update – Completion

We are excited to announce that your boat is now completed and moved to the storage yard, ready for shipping.

Please see below for some photos of the boat in her final days before being shipped. Let us also take you on a tour around your boat via thisĀ Youtube video.

It has been a pleasure building your boat and on behalf of the entire team at Seawind Catamarans, we wish you many years of fun-filled enjoyment aboard your new Seawind 1370.

Production Update – Fit out

Your boat is progressing well in the last phase of Fit out stage.

We recently completed the deck hardware, windows, hatches, and steering system.
Our Production Team is currently work on plumbing, LPG and electrical system. Timber fitout is at 90% of completion.

Production Update – Fit out

It is exciting that your boat is progressing well in the Fit out stage.

Our Production team is working on deck hardware (75%), windows & hatches (80%), steering (50%), electric work (70%), plumbing & LPG (70%), timber-fitout (50%), and on-going with small details gelcoat repair.

Production Update – Assembly

Your boat is progressing well in the Assembly stage.

We recently completed the hull – deck join, and window liner installation.

Our Production team is currently working on gelcoat repair, window installation, thru-hull fittings, engine, aircon, deck hardware, steering system, and plumbing system.

Production Update – Assembly

We are excited to inform you that your boat has been moved to Assembly stage.

The hull was demolded and our Assembly team is installing the furniture modules. The deck has targa bar and coach roof installed. With this progress, the hull and deck will be ready to be joined soon.

Production Update – Lamination

An exciting journey has started. Your boat is making progress in the first stage of production – Lamination.

Our Lamination team is laying the fiber inside the hull mold. The deck will also be started soon.